Sweden's Ringhals 4 nuclear outage extends into winter months

Sweden's Ringhals 4 nuclear outage extends into winter months
Sweden's Ringhals 4 nuclear outage extends into winter months Copyright  Thomson Reuters 2022
Copyright Thomson Reuters 2022
By Reuters
Published on
Share this article Comments
Share this article Close Button

OSLO - Swedish utility Vattenfall said on Tuesday it had delayed the restart of the Ringhals 4 nuclear reactor by two months to Jan. 31, in a further setback to power supply in the Nordic and Baltic region.

"The unforeseen required repairs are taking more time than expected, before starting up the unit after the yearly maintenance," Vattenfall said in a regulatory filing.

The extended outage comes at a critical time as energy prices soar across Europe and countries scramble to ensure there is enough power output for the coming winter.

"This worsens an already difficult power situation in southern Sweden," power market analyst Tor Reier Lilleholt at Norway's Volue said.

Vattenfall had already extended ongoing maintenance at Ringhals 4, which has an installed capacity of 1,130 (MW) by three months at the end of August, citing damages to a key component during testing.

Pontus de Mare, Head of Power System Operations at national grid operator Svenska Kraftnat said the import need would increase to 149 hours, from 36 hours normally, if Ringhals were to stay idle throughout winter.

With the current extension, risks of power shortages and blackouts in southern Sweden had increased, he said, while prices could soar.

"If we get a big import need, and it's difficult to get hold of enough effect while demand is very high, prices will shoot up very high single hours, single days. Prices can become extreme," he said.

The damage to the reactor's pressure vessel, a radioactive component, means that Ringhals must now build a full-size mock-up of the 12-metre (39 feet) tall structure for training before repairs can take place.

On the mock-up, Ringhals will also test work methods, components and special tools that will need to be produced for cleaning the pressure vessel and installing new spare parts, the operator said.

Lilleholt said the Ringhals 4 outage could also put pressure on prices in neighbouring countries.

"If we have a cold winter, this could lead to extreme effects in the market as it would be difficult to replace this power," he said.

Go to accessibility shortcuts
Share this article Comments

Read more

Moscow says it tested Poseidon underwater drone, another nuclear 'super weapon'

Sudanese paramilitary group accused of killing hundreds in North Darfur hospital

North Korea boasts of cruise missile test as Trump visits South Korea