Exxon to complete Baton Rouge, Louisiana, FCC work by April 5 -sources

Exxon to complete Baton Rouge, Louisiana, FCC work by April 5 -sources
Exxon to complete Baton Rouge, Louisiana, FCC work by April 5 -sources -  Copyright  Thomson Reuters 2022
Copyright Thomson Reuters 2022
By Reuters
Published on
Share Comments Add Euronews on Google
Share Close Button

HOUSTON -Exxon Mobil Corp plans to complete an overhaul of a gasoline-producing fluidic catalytic cracker (FCC) at its 502,500 barrel-per-day (bpd) Baton Rouge, Louisiana, refinery by April 5, sources familiar with plant operations said on Thursday.

ADVERTISEMENT
ADVERTISEMENT

Exxon shut the 110,000-bpd PCLA 3 FCC on Feb. 25 for the overhaul, which was scheduled to take seven weeks to complete.

"The Baton Rouge Refinery has shut down some of its units and associated operations for planned maintenance," said Exxon spokesperson Julie King on Thursday. "We have communicated this turnaround to our customers and expect to meet all contractual commitments."

The firm also plans to shut in April a 45,000-bpd diesel hydrotreater for planned work that will last until mid-June, the sources said.

PCLA 3 is one of two 110,000-bpd FCCs at the refinery.